The following provides general project information/updates and maps to help navigate around the work zones.
10-13-23
Crews continue more storm drain and utility work, retaining wall construction, sidewalk and driveway installations, and prep for road reconstruction along portions of 2600 North.
ROADWAY PAVING
Crews are scheduled to start paving the roadway with new asphalt along 2600 North (from 1550 W to 860 W) beginning Sunday, October 15. This paving is expected to last 3-4 days. Expect traffic restrictions and delays throughout the paving process.
More curb and gutters are also scheduled to be poured from 900 West to 600 West beginning Monday, Oct 16.
ALTERNATE/DETOUR ROUTES
The following are roads designated as alternate/detour routes to help navigate around the construction zones:
4000 North/Harvey Blvd (900 West for access north of 2600N)
1800 North (1300 West or 600 West for access south of 2600N)
See map below